Select Page

The Mt Lukens Building

By:

The project of building our flagship tower site at Mt Lukens started a long time ago in a galaxy far-far away.  It was 1982-1983 when we first identified the need to have our own building.  We were operating repeaters at Mt Lukens starting in the late 1970s in the Mobile Communications Service building.  The site was not a bad building from the amenity standpoint, but was not an especially good building either.

We had approximately 4 repeaters at Mt Lukens.  This is hardly a sufficient number of repeaters to justify building our own facility.  We installed these repeaters starting in late 1977 and slowly added the additional repeaters over time.  Eventually we had all four repeaters operating.  Unfortunately, we were in competition with the building owner in the radio sales and service business, so we knew that eventually this was going to reach a boiling point.  We looked at moving our repeaters to another facility at Mt Lukens and had established a relationship with another building owner in case we needed to pull the trigger to move our equipment.  Eventually, we got to that point where we needed to execute the move so we signed an agreement with the other building owner and proceeded to move our equipment.

We stayed in this newer facility for several years while we continued to build up the amount of equipment that we had at the site.  We were up to over 30 repeaters at Mt Lukens and continued to grow our business there to the point that it was obvious that we needed our own facility.  We had been working on the plans for our new facility for several years in the background while we were conducting normal business.  The US Forest Service who owns the property had a moratorium on building new facilities going back to the 1970s while they were working on their new site management plan which was intended to analyze the present and future need for communications at the site.  The new management plan & report identified where the existing facilities were located, what they liked, what they disliked, what needed to be upgraded and who was going to pay for the upgrades.  The management plan also identified potential locations for new facilities for two way radio and for microwave communications.

MRA took the finished report which came out in 1982 and immediately embarked on the project of obtaining a permit.  There were many obstacles to this process including the need to participate in the cost sharing of the new underground power system that was going to be installed at the site.  The existing overhead power lines were causing issues with the ability to place buildings and towers on the mountain and created reliability problems in adverse weather.  All of the existing building owners needed to contribute to the cost of building the new power system (the US Forest Service did not pay for anything) and new building owners had to contribute a prorated amount depending upon when the new facility was built and energized.

There were multiple obstacles to getting a permit which included those from the US Forest Service and some from the County of Los Angeles where the site was located.  A portion of the peak is within the city limits of the City of Los Angeles which would subject any construction in that portion of the mountain to obstacles from the City of Los Angeles.  Fortunately, the location that we proposed was within Los Angeles County who is easier to handle than Los Angeles City.  The first obstacle was obtaining a registered professional engineer to design the building.  There were some existing building foundations that were built by MCI in the 1970s which were abandoned by them.  They were building a new microwave network from Los Angeles to San Francisco when they made a deal with another company that already had an existing network with those facilities, so they stopped construction in the middle of the job and walked away.  At Mt Lukens, they had planned to use a prefabricated building on a concrete pad with a 100’ tower to hold the microwave dishes.  They had built the concrete pad for the building and the tower foundations for the tower at Mt Lukens and then abandoned the project.  So when we identified that location for our project, we “inherited” the existing improvements to our gain or our detriment, however it would ultimately turn out.  My goal was to make use of the improvements to save us considerable money building the project, but that turned out to be wrought with problems.

I worked every angle to keep the price down for designing the building and obtaining the permits.  This included coordinating between the different “experts” that needed to be involved, running paperwork to the US Forest Service and to LA County.  We hired an engineer to design the building who never left his office.  Any time he needed a question answered, I performed the research, went to the tower site, called the County engineer, contacted the US Forest Service to get the clarification that was needed.  I took the measurements of the concrete pad and the foundations and essentially performed the tasks of the surveyor to avoid the costs of sending a surveyor to the site.

Another task that I performed was to research the engineering from MCI for the tower foundations and the concrete pad.  I made literally over one hundred calls to MCI and their engineering firms attempting to find out anything that I could get on the existing improvements.  If I could get the information, we could potentially make a case for reusing the improvement.  If we were unable to get the information, it looked like we would have to remove the improvements at our expense and start over which would cost us a considerable amount of additional money.  I spoke to multiple people at MCI and their engineering firm.  Eventually, I found the actual engineer that designed the project.  He was very helpful, but we spent a considerable amount of time trying to identify the Mt Lukens site.  They had the project filed under the city name of La Crescenta while I kept insisting it was called Mt Lukens.  I offered a city name of La Canada / Flintridge which is the nearest city, but they could not find the project under that name.

The project engineer sent me a set of plans showing the engineering for the different towers and buildings within the entire project network.  This consisted of many of pages of blue prints which had multiple sizes and dimensions for the different sites within the network.  What I was missing was the “master” pages that showed the specifics of the tower site along with the engineering calculations that supported the specific dimensions that were selected for the project.  It took six months to eventually identify the plans which were filed under La Crescenta, but once they were found, they sent me a copy of the pages which provided the glue that held everything together from an engineering standpoint.  I then submitted these plans to our engineer who had to determine if he could reuse the improvements.  He was able to address the use of the existing concrete pad, but he could not address the issue of the tower foundations which had to be evaluated by the tower company.  So I sent the plans to the tower company for their evaluation.  They in turn decided that they needed a soils evaluation which required sending a drilling rig to Mt Lukens to take a core sample to look at the ground compaction and the specifics of the material that made up the soil to determine its ability to withstand the pressures that would be exerted on the foundations.

We managed to get the results of the different facets of the engineering one at a time.  First, the architect / engineer for the building decided that the concrete pad was sufficiently strong that it could support the concrete block building, so we could reuse the concrete pad.  Then we heard from the tower company that the concrete foundations contained sufficient strength to support our 120’ tower, even though the original tower design called for a 100’ tower.  As it turned out, the standard for engineering was to have a 2:1 safety factor in the design, but MCI had designed the tower foundations for a 3:1 safety factor.  When you took into account the fact that our tower was taller than the original design, we still had greater than a 2:1 safety margin in the design.  However, this did not account for whether or not the foundations would continue to stay in the ground.  After waiting for the soils company to provide their report, we found out that the soil was strong enough to keep the tower foundations from pulling out of the ground.

Finally, we thought that we were in the clear, but that did not last.  As we proceeded through the processes, we submitted the plans to the US Forest Service for their approval.  They took about 30 days to review the plans and determined that the plans were acceptable.  However, they still required us to go to LA County building department to get the building plans checked for structural integrity.  Upon arriving at LA County, the building department decided that we had to pass plan check from the planning department to determine if we would be allowed to build the tower and if it complied with their laws.  I informed them that the US Forest Service had approved the plans and since it was on federal land, they were exempt from LA County planning department.  They disagreed with me and claimed authority over the planning portion of the project and flatly refused to perform a plan check for safety until after it went through LA County planning.  I left their office with my tail between my legs and had to think about how to handle the situation.

I slept on the problem and decided I had to contact the US Forest Service to see what could be done.  So I took the plans to their office in San Fernando and they informed me that they were exempt from local regulation which is the same thing that I told LA County to no avail.  I asked if they could write a letter to LA County regarding the lack of jurisdiction.  They said that it would take 90-180 days to get that done so I left there thinking what else could be done.  We were trying to move the project along at a faster pace because we were looking at installing significantly more equipment at Mt Lukens and we were already paying a considerable amount of rent which is significant today and was far more significant in 1987 dollars.

After sleeping on my meeting with the US Forest Service, I came up with another idea.  I called the US Forest Service and got the local Forest Ranger on the phone instead of speaking to the staff who I had interfaced previously.  I told the Forest Supervisor that some local bureaucrat at LA County has decided that he knows better than you how to run your forest.  This angered the Forest Supervisor who was now out for blood.  I gave him the name and phone number of the person at LA County that gave me the trouble with the building permit and he received a scathing call from the Forest Supervisor who reamed him a new hind end, then stopped being nice about it and continued the reaming until the LA County employee was a worthless pile of mush.  I then went back to the LA County offices to resubmit the plans for approval.  This time, I received a warm reception with a complete willingness to process my plans.

Out of the woods yet?  Of course not!  The LA County building department returned the plans for a few minor corrections plus one zinger.  They described a disruption zone from the tower foundations that would rise from the bottom of the foundation at a 30 degree angle towards the building that would house the equipment and would apply pressure to the foundations.  They wanted to see some engineering to determine that the disruption zone would not disrupt the building.  So now the plans went back to the engineer / architect for the minor corrections and the appropriate calculations and proof that the tower foundations would not cause trouble for the building.  At last, I thought that we had covered all the bases so then I went to resubmit the plans.

Two weeks went by and finally I received a call from LA County telling me to pick up the plans for additional corrections.  I thought that I had covered all the bases, but I headed over to their offices in Arcadia which is not an insignificant drive from our offices.  When I reviewed the return, they were telling me to pay a new tax that just went into effect that would provide additional funding for the local school.  Mt Lukens is not located with any school district, so I questioned them as to whom I was supposed to pay this tax of $150.  It was new to LA County, so they also didn’t know whom to pay.  So I got them to agree that I would pay the fee to the La Crescenta School District.  So I went back to the office to get a check made out to the school district and then proceeded to drive over there to pay them the fee.  When I arrived at the district headquarters, I was bounced around between about 5 different staff members before it was decided who could handle the situation.  They were completely taken off guard as no one had ever been there before to pay them this new tax.  I had to convince them that I had to pay the tax and I needed a receipt that I had paid them the money.  This took awhile to get someone to actually decide to accept the money and write me a receipt.

Now that I was armed with the proof that I paid the school tax, I went back to the Arcadia offices of LA County.  I brought the plans with me and insisted that they issue the permit while I stood there for the next 45 minutes.  I was proud of myself that I was able to leave their offices with the stamped plans.  So now I had to submit the stamped plans to the US Forest Service so that they knew that we had obtained the building permit.  After another week, I had a letter from the US Forest Service giving us permission to proceed with the construction.

While this process was going on, I had generated copies of the plans and had circulated the plans to several construction companies to have the plans bid.  We had received the bids, evaluated them, met with the contractors to discuss the bids and selected the winning contractor, Gianni and Associates who had built several radio buildings and towers for cellular companies.  They were not the low bid as their bid was the middle price, but we had the most confidence in their ability to complete the project in a timely fashion as the cellular companies were not very forgiving about delays in getting their sites online.  We had seen their work and felt that they did quality work and the owner was east and flexible.

We still were not quite ready to start.  I was simultaneously working with the bank to finance the building.  The problem with financing was the fact that we did not receive a lease which is the document that the bank wanted to see.  The US Forest Service at that time issued what they called a Special Use Permit.  It is essentially the same as a lease but did not contain a few provisions that one would see in a traditional lease and it said “Special Use Permit” instead of “Lease”.  This scared the banks and we had a bad time trying to get the bank to finance the project.  We had worked with Mid Cities National Bank attempting to finance the building and the loan officer left the bank and landed at Downey National Bank.  We moved all of our accounts to Downey National Bank and continued the process which finally resulted in a denial.  We did get financing, but it only happened by using our personal real estate as security for the loan instead of the new radio building.

After all of those ordeals, we were finally off and running with the project.  These processes took over 5 years to complete from the time that the new underground power had been installed at Mt Lukens which gave us the advantage that we no longer had to retroactively contribute to the new power system costs.  So we ordered the radio tower to fit the foundations and we hired Gianni & Associates to start the construction.  We had a goal of occupying the building by June 1, 1988 to avoid another month’s rent in the building where our equipment was currently located.  We had approximately 25 repeaters to install in the new building and needed to have them on the air in June and we did not want to install them in the old building and then within 30 days have to move them, so we kept looking for ways to get the construction done sooner rather than later.

We started the construction by meeting Jim Gianni (the owner of the construction company) at Mt Lukens to look at the plans at the construction site and go over the details of how to proceed.  The first thing that we did was to look at the surface of the concrete in the pad and noted that it had deteriorated and would need to be resurfaced.  We then took measurements of the concrete pad and discovered that it was not square which meant that we could not use it without a lot of work.  We decided to add one block to each dimension of the building and would dig new foundations around the pad so that the existing pad would become nothing more than fill dirt.  We also noted that the ground was level at the pad, but quickly sloped away from the pad which would cause us some difficulty during construction.  We also noted that the elevation contours were not on the plans since we did not pay for a surveyor to survey the site prior to the preparation of the plans.

Certain aspects of the construction were left out of the bid to the general contractor.  We had hired an air conditioning company to install the central air conditioner for the main room and the wall mount air conditioners for the smaller rooms.  The main air conditioner needed a custom frame to raise it off the ground so that it did not get buried in snow or anything else and the wall mount air conditioners had custom made hot dipped galvanized boxes to house and secure the air conditioners.  These boxes were designed in such a way that they needed to be installed in the wall as the wall was being built, so they had to be ready once the block was raised to the height that required the air conditioners to be installed.  The cable entry boxes were custom made and built for our building by the air conditioning contractor who had the fabrication facilities to make these custom entry boxes.  These boxes were exactly two blocks tall and two blocks wide and had five sides which would fit into the block walls and be almost impervious to thieves being able to break into the building through the cable entrances.  The electrical contractor was one of our customers whom we hired directly to install the main electrical panel and all of the sub panels.  Most of the branch circuits were not included, but lighting and convenience outlets were included in the basic electrical contract.

Now it was time to start the actual construction.  A backhoe was obtained to dig the foundations for the entire building.  Since we were able to reuse the existing tower foundations, we did not have to dig at the tower location.  After the foundation was dug, it was time to install the underground conduits to bring in the power from Edison and the telephone cable from General Telephone.  We also had to dig the foundations for the propane tanks and the trench for the propane line that goes from the propane tanks to the building.  After that was completed, the rebar was installed in the foundation and the electrical contractor showed up to install the U-fer ground for the building.  At this time it occurred to me that we had not planned anything for the ground of the building and tower, especially when the digging of the foundation exposed the halo ground that was installed for the concrete pad.  So now I was faced with creating a ground system before it was too late.  So I purchased a large amount of wire and connectors to create a ground system that would provide a reliable low impedance ground for both the building and tower.  I installed the ground system before the concrete trucks showed up to pour the foundation.

Soon, we were pouring the foundation and unloading a truck of concrete block.  The block was used to build the foundation to just above the height of the floor so that the block would act as the forms for the concrete floor.  It was now time to place sand on top of the existing concrete pad so that the new concrete did not bond to the old concrete and create a problem in the future.  Once that was done, the rebar and screen was installed to secure the concrete pad of the floor so that it would be strong, not crack and not move.  We worked with the concrete crew to get the floor level which would make our future job of installing the rack and cable tray much easier.  After a few days of drying and hardening to the point where we could drive over the slab, the air conditioning contractor brought the air conditioner up the mountain and drove the massive air conditioner unit across the floor to place the unit into the “patio” area at the rear of the building.  If we had not done this, we would have to hire a crane to pick up the air conditioner and transport it over the top of the building because that area would no longer be accessible.  The air conditioning contractor had also manufactured the cable entry ports and had the ports hot dipped galvanized.  He delivered the ports at the same time that he delivered the main air conditioner to the site so that they could be installed in the walls once we had the block walls ready for them to be installed during the construction.

Once we started building the walls, we noticed that the rear of the building was specified to be built with 6 inch block.  Although this was strong enough for the current job, it would be insufficient for a future expansion of the facility which we were anticipating to happen at some point in the future.  Therefore we made a decision to upgrade the block from 6 inch to 8 inch.  We also decided to upgrade the door to the battery room from a chain link gate to an actual door to reduce the dirt and dust that would enter the room with a chain link gate.  As time went on, we saw other items that needed to be upgraded so that the finished product would be a quality building that would last a long time without concern about high maintenance issues.

Now that we had the air conditioner in place, it was full speed ahead building the block walls.  The normal procedure was to build 4 feet of wall and then call for inspection.  However, due to the remoteness of the building, the building department gave permission for us to build 6 feet of wall before calling for inspection.  The concrete for the mortar was mixed on site during the process of building up the block walls.  However, we needed to pour all the cells of the block which meant that we needed a concrete truck to bring a load to fill the walls.  Once that was done, we were ready to call for inspection.  The inspectors did not have 4WD vehicles which could navigate the roads to the site, so it was necessary to meet the inspectors at the bottom of the mountain and take them up the hill for the inspection and take them down the hill after inspection was finished.  The inspector gave permission for the next lift to be another 6 feet which would complete the walls so we were able to get by with only two inspections on the block walls instead of three inspections that would normally be required.

Now it was time to get delivery of more concrete block.  The truck was dispatched to bring the block and we had to meet the truck at the bottom gate to let the truck through the locked gate and escort the truck up the hill to the site.  We worked with the truck to get the block unloaded around the building to reduce the amount transport of the block to the place where it was to be used.  Once the block was on site, the block workers could start working on the block again working on one row of blocks after another working up the walls to the point where the door frames needed to be installed and the air conditioner security cages for the wall mount air conditioners needed to be installed.  As the walls continued to be raised, we got to the point where the holes for the cable entry ports had to be left open for the ports to be installed at a later date.  (The holes in the cable entry port had been punched too small so we had to take them down the mountain to have them re-punched which made them unavailable at the time that the block layers were ready to install the entry ports.)  The block continued to be raised one row of block at a time until we reached the full height of the wall in the front of the building.  Then they went to work raising the height of the block on the south side of the building, the battery room and the patio area.  Eventually, the block was up to the full ceiling height.

Mount Lukens TowerWhile the building was proceeding, it was time to get the tower company out to install the radio tower.  First we had to get delivery of the tower steel which was manufactured by Rohn and shipped from the east.  We had the truck meet with the tower company at the bottom of the hill where they unloaded the tower pieces onto the ground and onto the truck from Conlan Engineering who was the company who had been contracted to provide the tower and install it.  They sent a crew that lived in a trailer parked at the bottom of the hill for a week while they built the tower.  The main tower pieces were loaded onto the Conlan vehicle and they transported much of the tower to the site.  After unloading the tower pieces at the site, they made another trip down the hill and brought the balance of the tower pieces up to Mt Lukens.  They proceeded to build the tower the old fashioned way, one piece at a time on site.  They did not have a crane.  They assembled each piece of the tower starting with the tower legs and continued to assemble the tower bracing until the first section was built.  They then assembled the gin poleMount Lukens Tower which consisted of two sections of Rohn 25 tower (which is triangular about 12” on a face) with the appropriate ropes and pulleys to secure the gin pole inside the bottom section of the tower.  The gin pole had a pulley at the top with a steel cable attached to a winch.  They would attach the heavy pieces of the tower to the cable and lift the tower piece with the steel cable that was attached to a winch on their vehicle.  First they would mount the first tower leg (after they assembled all the climbing pegs) to the leg of the 20’ bottom section.  Then they would use the pulleys that secured the gin pole in place to move the top of the gin pole over the second tower leg and use it to lift the second leg so that they could bolt it into place.  Then they would move the gin pole over the top of the third leg and bolt it in place.  After the three legs were standing up above the lower section, they would install the braces one at a time using the gin pole to winch these heavy pieces up the tower and hold them in place while one of the workers would insert the bolts that hold the tower together.  They would then proceeded to assemble the next section of the tower and continued working their way up the tower until they had the entire structure assembled. blank

Now it was time to start the roof framing.  A truck load of lumber needed navigate the windy and twisty road up to the site and unload the lumber at the site.  Extra long roof joists were ordered to span the 20 feet from north to south to provide a ceiling without any center supports.  The joists were designed to be on 12 inch centers and blocked every 4 feet which presented challenges for the framers because the 12 inch spacing made it difficult to swing a hammer.  So they Mount Lukens site contructionworked through the framing from one end of the building to the other installing each ceiling joist one at a time until the entire framing job was finished.  Now it was time to put the roof panels on top of the roof to start the process of making the roof secure and waterproof.  However, we were running into a time problem with getting the building ready to occupy by June 1st, so we told the general contractor to install the plywood panels on the bottom of the roof joists so that we could finish the interior of the building and get it ready for the electrician to install the power panels and the lighting.  This was an abnormal order of events as the GC would Mount Lukens Site Constructionnormally install the plywood panels on top of the roof, then the waterproof layer before attempting to finish the interior of the building.  But we had a time table to meet so this process was a better fit for us which allowed us to have the finished floor installed along with the electrical lighting so that we could proceed with the installation of the 6 rows of racks with 9 racks per row for a total of 54 racks in the main room.  Therefore, the interior of the ceiling was finished first and then the contractor went to work installing the insulation between the roof joists.  After the insulation was installed, they proceeded to lay the 1 inch plywood over the top of the ceiling joists, then install the waterproof layer and finally install the corrugated metal over the top of the roof to complete the waterproof layer to make the building water tight.

While the roof framing was being done, it became apparent that we needed to get the cable port entries installed.  The holes punched in the entry port had their size corrected and the Mount Lukens Buildingunits had been brought back to the site.  Four of the entry ports were to be installed in the main room and one cable entry port for each of the smaller private rooms in the front of the building.  Each of these entry ports were 16” high by 32” wide which represents 2 blocks high by 2 blocks wide.  When the block layers left the space for the cable entry ports and poured the centers of the blocks, some of the concrete slopped over the top of the cells of the block at the bottom of the entry port space leaving a small hump.  Also, at the upper edge of the entry port space where a 2” x 8” piece of wood held up the block above also had concrete leak out of the bottom of the center area of the block.  This meant that the opening was slightly too small for the cable entry port that was built to exact dimensions of 16” by 32” and would not fit into a smaller space.  So the only solution was to chisel the concrete where it poured out of the block center working my way all around the hole for the cable port.  This seemed to be an endless task as the concrete did not chisel easily.  After spending a huge amount of time chiseling the hole, I finally managed to get one cable port entry panel to fit into the wall.  Now I had one down with only six more to go to get all seven of the entry port panels installed into the wall.  It easily took the better portion of two days to get all the cable entry ports to fit into the walls.  Once they were in place, we then had to drill the concrete to install the anchors that would hold the cable entry ports in place.  Once the anchors were installed, it was time to use caulk to seal around the entry port so that the weather, bugs and other unwanted critters stayed on the outside of the building.

Mount Lukens cable tray and SchoonerThe next project was to install the cable tray on the outside of the building.  The cable tray needed to be hauled up to the mountain along with the cable tray support brackets which were 3 foot long pieces of back to back strut with a mounting plate welded to the end of the strut.  The entire assembly was hot dipped galvanized along with the cable tray so that it would survive being outdoors.  First we needed to locate the positions for the mounting brackets.  Then we needed to mount the strut brackets to the block wall which would support the cable tray just below the cable port entries on the front and the side of the building.  We carefully measured the location of each mounting strut bracket and proceeded to drill the block to install the concrete anchors.  Two anchors were required for each bracket.  Then we placed the tray on top of the supports and the tray was cut to length and assembled.  This provided a method of supporting the cable outside the building to the tower.

Now that the building interior was finished, we were able to proceed with the installation of the racks.  Each row of racks was carefully positioned according to the plans which allowed for ample space between rows of racks to facilitate ease of servicing.  Keeping the rows straight required following a “chalk line” which consisted of the Lukens equipment rackslines from the floor tiles and carefully drilling the holes to install the concrete anchors to secure the racks in a straight line for a quality job.  Each rack required drilling 4 holes and installing 4 concrete anchors which totaled 36 concrete anchors per row or 216 anchors for all the racks.  Once the first row of racks was completed, we installed the second, third and continued until the 6th row of racks was complete.  Then it was time to install the cable tray so that it properly secured the top of the racks while providing the proper path for the antenna cables to be brought into the building and Mount Lukens cable traysdistributed around the building as required.  The cable tray formed an XY grid which ran the length of the building from the cable port entry panels on the east end of the building to the opposite end of the building where it attached to the far wall with cable tray feet on the west side of the building and it ran from side to side along the tops of the racks where it secured to the south wall on one side of the building and to the north wall on the other side of the building.  This made the racks incredibly strong so that they did not move at all and would stand up during the most violent earthquake.

Mount Lukens Equipment racksThe next task was to get the electrical power wired in the room.  The electrical contractor had been contracted to bring the power into the room by installing the two power panels that were specified on the plans.  They had also been contracted to install the lighting on the ceiling and install some convenience outlets around the room.  They were not contracted to install the branch circuits from the power panels to the equipment racks.  At the same time, we were busy working on the radio tower installing the antenna cables from the specific location on the tower to inside the room where they were to connect to the master receive antenna systems, the transmit combiners and other cables that needed to be installed for individual radios.  This left us no time to install the branch circuits that we had originally intended to install ourselves.  So we decided to have the electrical contractor proceed with installing most of the branch circuits.

Now we had the time to continue working on the antenna systems on the tower.  The main receive cable that we installed was 1 5/8” for our 800MHz master receive system (1 cable) to reduce signal loss.  We installed 1 ¼” cable for all of the 800MHz transmit combiners (7 cables) for the same reason.  These cables are large and difficult lift up the tower due to their significant weight, hard to bend, difficult to install the connectors and very Mount Lukens Towerexpensive to purchase.  The 900MHz receive (1 cable) and transmit antenna systems (15 cables) followed a similar pattern which produced an antenna system that has superior performance over the competition.  The UHF master antenna system was also installed with 1 ¼” cable for the master receiver system (1 cable) and 7/8” cables for the master transmit combiner systems (7 cables).  We had purchased several new antennas and installed them in place to make the antenna systems fully functional and ready to operate without having to take them from the old building to get the systems operational.  We had installed the new Sinclair UHF folded dipole antennas that were very broadband which would allow us to feed a wide range of frequencies into the transmit combiners.  On the 800MHz band, we used a similar approach to install antennas that would cover the entire range of frequencies available to the 800MHz band.  On 900MHz, there were unique challenges because the method that the FCC used to assign channels.  Most licensees at 900MHz obtained 10 channels that were close spaced together and could not be combined together without high loss from the transmitter to the antenna.  MRA took a very different approach that delivered low loss from the transmitter to the antenna because we had arranged for 50 channels to occupy our building.  This allowed us to use low loss transmit combiners that took the first channel fromMount Lukens 800MHz combiners system 1 and combine it with the first channel from system 2, system 3, system 4 and system 5.  This gave us considerably higher radio signal levels from each transmitter using less power and getting more transmitters per antenna than Motorola.  This was a total mystery to Motorola and others in the radio business.  (A year later, Motorola sent their engineers over to see our building to find out how we managed to outperform their systems by a significant margin.)

Installing the transmit combiners was a considerable amount of work which took many days to complete.  However, we also needed to install the master receive system for the three different bands.  The receive filters  for 800MHz and 900MHz were relatively simple devices that took a small amount of effort to install.  The receive distribution system for the two bands were custom ordered which took 10 weeks to get delivery of the filter.  The receiver distribution had to be powered and installed which took a day to accomplish.  The receive Mount Lukens UHF transmit combiners and master receive filtersfilter for the UHF band required multiple sub-bands which necessitated a custom filter design that allowed one receive antenna to serve multiple sub-bands.  This filter contained over 60 cavity filters for a total of 5 sub-bands which included 440-445MHz (amateur radio), 456-460MHz (450MHz sub-band), 466-470MHz 460MHz sub-band), 474-476MHz (470MHz sub-band) and 510-512Hz (500MHz sub-band).  The filter took about 14 weeks to be manufactured, tuned and delivered to the site.  It took two people a day to install and make operational along with the master receive distribution system which consisted of special low noise pre-amplifiers from Angle Linear and splitters to provide signal to 36 receivers.  They run directly from 12 volts, so they were powered from the battery system as described below.

Another item of the building that needed to be addressed was the battery systems.  We had a room that was 14’ long by 6’ wide which was intended for batteries to keep the equipment working if we lost power in the building and the generator did not function.  We installed the battery rack in the building which was a job for 3 people that took all day.  Once the rack was in place, we brought the batteries up to the site and had to place them on the battery rack.  The batteries that we had were used telephone company central station batteries which weighted 604 pounds for each cell in the battery system and there Mount Lukens Batterieswere 7 cells for the system which provided 14 volts instead of 12 volts.  This provided a higher voltage that would make the repeaters operate more reliably, but it creates other problems such as the fact that most battery chargers are expecting a 12 volt battery system.  (There are other problems that are too technical to delve into at this time with a 14 volt battery bank.)  We also installed a fuse panel, battery chargers to keep the batteries charged and power distribution panels at every row of racks to distribute the battery system around the room so that it is readily available to any piece of equipment within the room.

Once we had all of the above systems built and installed, it was time to start installing the new 900MHz equipment.  This was the equipment that we did not want to install in the old building and then have to remove and reinstall once the building was finished.  So we started installing the 900MHz repeaters in the new buildings while making the equipment look like a professional installation.  We had 20 channels to install which took quite some time so we worked on it diligently until the job was done.  Once that was finished, we needed to move our existing 800MHz equipment from the old building to our new building.  The system was very busy and therefore, we could not move the equipment during the normal work day.  In fact, the equipment was busy on Saturday and Sunday, but Sunday was the least busy day.  So we notified the customers that the system would be off the air for the move and arranged with our people to be up on the mountain on a Sunday morning where we started moving the equipment around 10AM and had the entire move completed by 12PM (noon).  Before we moved any piece of equipment, we made certain that it was properly labeled so that we could easily identify which repeater it was so that it could be installed in the new building in the least amount of time.  Mount Lukens LTR RepeatersWe had people at the old building removing the equipment out of their cabinets, collecting the radios and transporting them to the new building.  We had other people at the new building mounting the repeaters into the racks that were already installed in a neat and orderly fashion so that one could easily identify the equipment and follow the wiring.  As a result of the system that we used, no individual repeater was off the air for more than one hour which kept the down time for the customers to a very acceptable level.  We never received any complaint from any of the customers about the system outage, a small miracle.

We now have completed the move of our 800MHz equipment, but we still had other equipment to move.  We had some UHF repeaters and some customer owned VHF equipment.  These repeaters had a far lower amount of usage, but the customers were still not happy about being off the air.  So we moved this equipment before 8AM in the morning or after 5PM in the evening, so that the radio equipment was available to the users during the normal work day.  Once the UHF repeater was moved and installed in the Mount Lukens Radio Repeater sitenew building, then we could work on removal of the ancillary equipment that was not reused in the new building during normal working hours.  This also included similar equipment from our 800MHz trunking system.  We still had a lot of work to do at the old site.  We needed to remove the radio cabinets, the antennas and the antenna cables from the 800MHz equipment.  In order to avoid being charged for additional rent, we had to remove all this equipment from the site.  Our lease said that we needed to leave the building as we found it, less normal wear and tear, so that is what we intended to do.  We disassembled the cabinets, removed the internal wiring, removed the antenna cables and removed the antennas from the tower.  Once we had all the equipment removed, we needed to seal up all the holes that we left open in the building and then it was time to notify the building owner that we had removed the equipment from the building as per the notice that we had given to them about our intention to vacate the building.

Now there was time to relax and work a more normal schedule.  We still had lots of new equipment to install in the building and get on the air, but the crash rush to make the move was over.  We still needed to get the backup generator operational and we needed to finish wiring the battery systems to all the repeaters.  We needed to clean up the wiring that was thrown in to get equipment on the air to facilitate the speedy move and we had low quality cables that needed to be replaced with more expensive high quality cables.  In all, there was shortage of items that still needed to be addressed so we continued the work on the building for another two months on an almost daily basis until the work was done.

It is difficult to count up the thousands of hours of work that went into the design, engineering and construction of the building and the wiring of the many systems.  The project took years to plan and month to build.  The radio systems outperformed themselves by a substantial margin compared to our previous location on the mountain.  It represented the single most profitable endeavor to date with our company, paying for itself in 2 years.  Most buildings take 10-30 years to pay for themselves, so the project was a resounding success on all fronts.

Now it was time to take a break from our crazy schedule, fall back and regroup.  Then it was time to work on the next tower site, radio system or customer need.  Another day’s work and another project to build………………………